Cost Of Yucca Mountain Nuclear Waste Repository

##title##
Although the location has been highly contested by both, environmentalists and non-local residents in Las Vegas, which is over 100 miles (160 km) away, it was approved in 2002 by the United States Congress. However, under the Obama Administration funding for development of Yucca Mountain waste site was terminated effective with the 2011 federal budget passed by Congress on April 14, 2011.

Spent nuclear fuel is the radioactive by-product of electric power generation at commercial nuclear power plants, and high-level radioactive waste is the by-product from reprocessing spent fuel to produce fissile material for nuclear weapons. In 1982, the United States Congress established a national policy to solve the problem of nuclear waste disposal. This policy is a federal law called the Nuclear Waste Policy Act, which made the U.S. Department of Energy responsible for finding a site, building, and operating an underground disposal facility called a geologic repository. The recommendation to use a geologic repository dates back to 1957 when the National Academy of Sciences recommended that the best means of protecting the environment and public health and safety would be to dispose of the waste in rock deep underground.

The Department of Energy began studying Yucca Mountain in 1978 to determine whether it would be suitable for the nation's first long-term geologic repository for over 70,000 metric tons (69,000 long tons; 77,000 short tons) (150 million pounds) of spent nuclear fuel and high-level radioactive waste currently stored at 121 sites around the nation. An estimated 10,000 metric tons (9,800 long tons; 11,000 short tons) of the waste would be from America's military nuclear programs. On December 19, 1984, the Department of Energy selected ten locations in six states for consideration as potential repository sites. This was based on data collected for nearly ten years. The ten sites were studied and results of these preliminary studies were reported in 1985. Based on these reports, President Ronald Reagan approved three sites for intensive scientific study called site characterization. The three sites were Hanford, Washington; Deaf Smith County, Texas; and Yucca Mountain. In 1987, Congress amended the Nuclear Waste Policy Act and directed DOE to study only Yucca Mountain, which is already located within a former nuclear test site. The Act provided that if during Site Characterization the Yucca Mountain location is found unsuitable, studies will be stopped immediately. This option expired when the site was actually recommended by the President. On July 23, 2002, President George W. Bush signed House Joint Resolution 87, (Pub. L. No. 107-200) allowing the DOE to take the next step in establishing a safe repository in which to store the country's nuclear waste. The Department of Energy was to begin accepting spent fuel at the Yucca Mountain Repository by January 31, 1998 but did not do so because of a series of delays due to legal challenges, concerns over how to transport nuclear waste to the facility, and political pressures resulting in underfunding of the construction.

On July 18, 2006 the DOE proposed March 31, 2017 as the date to open the facility and begin accepting waste based on full funding. On September 8, 2006 Ward (Edward) Sproat, a nuclear industry executive formerly of PECO energy in Pennsylvania, was nominated by President Bush to lead the Yucca Mountain Project. Following the 2006 mid-term Congressional elections, Democratic Nevada Senator Harry Reid, a long time opponent of the repository, became the Senate Majority Leader, putting him in a position to greatly affect the future of the project. Reid has said that he would continue to work to block completion of the project, and is quoted as having said: "Yucca Mountain is dead. It'll never happen."


Site of the Yucca Mountain


yucca-drawing The Nuclear


The Yucca Mountain Project


is an enormous sunk cost,


U.S. Nuclear Regulatory

In the 2008 Omnibus Spending Bill, the Yucca Mountain Project's budget was reduced to $390 million. Despite this cut in funding, the project was able to reallocate resources and delay transportation expenditures to complete the License Application for submission on June 3, 2008. Lacking an operating repository, however, the federal government owes to the utilities somewhere between $300 and $500 million per year in compensation for failing to comply with the contract it signed to take the spent nuclear fuel by 1998.

into Yucca Mountain,


The Yucca Mountain repository


storing nuclear waste?


storage of nuclear waste.


Work at Yucca Mountain,

During his 2008 presidential campaign, Barack Obama promised to abandon the Yucca Mountain project. After his election, the Nuclear Regulatory Commission told Obama he did not have the ability to do so. On April 23, 2009, Lindsey Graham (R-South Carolina) and eight other senators introduced legislation to provide "rebates" from a $30 billion federally managed fund into which nuclear power plants had been paying, so as to refund all collected funds if the project was in fact cancelled by Congress.
The purpose of the Yucca Mountain project is to comply with the Nuclear Waste Policy Act of 1982 and develop a national site for spent nuclear fuel and high-level radioactive waste storage. The management and operating contractor as of April 1, 2009 for the project is USA Repository Services (USA-RS) (a consortium of government contractors, URS Corporation, Shaw Corporation and Areva Federal Services LLC). Following the layoff of 800 employees on March 31, 2009, the consortium had about 100 employees remaining on the project prior to all being laid off by the end of the 2010 financial year due to zero funding in President Obama's 2011 budget for the Office of Civilian Radioactive Waste Management. Sandia National Laboratories had the scientific responsibility for post closure analysis and ensuring compliance with the NWPA for one million years. The main tunnel of the Exploratory Studies Facility is U-shaped, 5 mi (8.0 km) long and 25 ft (7.6 m) wide. There are also several cathedral-like alcoves that branch from the main tunnel. It is in these alcoves that most of the scientific experiments are conducted. The emplacement drifts (smaller diameter tunnels branching off the main tunnel) where waste would have been stored were not constructed since they required a construction authorization by the Nuclear Regulatory Commission. The repository has a statutory limit of 77,000 metric tons (85,000 short tons). To store this amount of waste requires 40 miles (64 km) of tunnels. The Nuclear Waste Policy Act further limits the capacity of the repository to 63,000 metric tons (62,000 long tons; 69,000 short tons) of initial heavy metal in commercial spent fuel. The 104 U.S. commercial reactors currently operating will produce this quantity of spent fuel by 2014, assuming that the spent fuel rods are not reprocessed. Currently, the US has no civil reprocessing plant. By 2008, Yucca Mountain was one of the most studied pieces of geology in the world with the United States having invested US$9 billion on the project. The Department of Energy (DOE) estimates that it has over 100 million U.S. gallons of highly radioactive waste and 2,500 metric tons (2,800 short tons) of spent fuel from the production of nuclear weapons and from research activities in temporary storage. The cost of the facility is being paid for by a combination of a tax on each kilowatt hour of nuclear power and by the taxpayers for disposal of weapons and naval nuclear waste. Based on the 2001 cost estimate, approximately 73 percent is funded from consumers of nuclear powered electricity and 27 percent by the taxpayers. The latest Total System Life Cycle Cost presented to Congress on July 15, 2008 by Director Sproat is $90 billion. This cost, however, cannot be compared to previous estimates since it includes a repository capacity about twice as large as previously estimated over a much longer period of time (100 years vs 30 years). Additionally, the cost of the project continues to escalate due to the lack of sufficient funding to most efficiently move forward and complete the project. In 2007, the DOE announced it was seeking to double the size of the Yucca Mountain repository to a capacity of 135,000 metric tons (149,000 short tons), or 300 million pounds.

Yucca Mountain nuclear waste


Yucca Mountain, Nevada


deposits in Yucca Mountain


Print. Aerial view of


term radioactive waste

The tunnel boring machine (TBM) that excavated the main tunnel cost $13 million and was 400 ft (120 m) in length when in operation. It now sits at its exit point at the South Portal (south entrance) of the facility. The short side tunnel alcoves were excavated using explosives. The U.S. Department of Energy was to begin accepting spent fuel at the Yucca Mountain repository by January 31, 1998. However, 12 years after this deadline, the repository at Yucca Mountain is still over a decade away from being opened, and the opening date continues to be delayed. Because of delays in construction, a number of nuclear power plants in the United States have resorted to dry cask storage of waste on-site indefinitely in nearly impervious steel and concrete casks. To keep these plants operating, it may be necessary to construct a temporary facility at the Yucca Mountain site or somewhere else in the West if opening of the underground storage continues to be delayed.

Cost of Yucca Mountain Nuclear Dump Soars. July 16, 2008


Yucca Mountain Fund Cut will


Moon Seen As Nuclear Waste


the Yucca Mountain Nuclear


Newt Gingrich, Republican